Question #172417

Shiv want to lay a track 200 m long and 6 m wide using a team of 60 boys in 2 days. After 1 day, Shiv find 75 m x 6 m track has been laid. How many men should Shiv hire additionally if 2 men do the job of 5 boys


1
Expert's answer
2021-03-17T17:12:22-0400

Solution:

Since, width is same all the time, so we are avoiding it and taking only length into account.

60 boys lay 200 m track in 2 days.

60 boys lay 100 m track in 1 day.

1 boy lays (1006=53)(\frac {100}6=\frac 53) m track in 1 day.

After 1 day, 75 m track is laid.

Remaining track = 200 - 75 = 125 m

Number of boys required to lay this =125×35=75=125\times \frac35=75

=15×5 boys=15×2 men [5 boys=2 men]=30 men=15\times 5\ boys \\=15\times 2\ men \ [\because 5\ boys=2 \ men] \\=30\ men

So, 30 men should be hired additionally.


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!
LATEST TUTORIALS
APPROVED BY CLIENTS