Answer to Question #153158 in Statistics and Probability for izah

Question #153158
1. A job with a 90% learning curve required 20 hours for the initial unit. The eighth unit should require approximately how many hours?

TN = T1C

2. A job requires 20 hours for the initial unit and 12.8 hours for the fourth unit. What is the learning rate?

TN = T1C

3. A job with a 95% learning curve required 19 hours for the second unit. The first unit should require approximately how many hours?

TN = T1C

4. The first product took 10 hours to build and the learning curve is estimated to be 90%. How long will it take to make the eighth unit?

TN = T1C

5. The first unit of production took 10 hours with a 90% learning curve. How long will it take to complete both the first and second units?

TN = T1C
1
Expert's answer
2020-12-29T12:28:20-0500
Dear izah, your question requires a lot of work, which neither of our experts is ready to perform for free. We advise you to convert it to a fully qualified order and we will try to help you. Please click the link below to proceed: Submit order

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
APPROVED BY CLIENTS