John can finish a painting job in 2 days. Peter can finish the
job in 3 days. Danny can do the job in 6 days. How long will
it take all of them together to finish the job?
It follows that John can do part of the job per one day, Peter can do part of the job per one day, and Danny can do part of the job per one day. Taking into account that
we conclude that it will take one day all of them together to finish the job.