3. The formula below is often used by projection manager to computer E the estimated time to complete a job, where is the shortest completion time, P is the longest completion time and M is the most likely completion time. E = (0 + 4M + P)/6 Which of the following correctly gives in terms of E ; , and M? a. P = 6E - O - 4M b. P = - 6E + O + 4M


1
Expert's answer
2021-04-15T06:34:07-0400
E=(O+4M+P)/6E=(O+4M+P)/6

Then


P=6EO4MP=6E-O-4M



a. P=6EO4MP=6E-O-4M