Answer to Question #256205 in Engineering for sfghjlad

Question #256205

In a certain computer system, five (5) processes A, B, C, D, and E are active with their burst times (in ms) of 8, 10, 2, 4, and 3 respectively. These processes come at times (in ms.) 16, 0, 4, 20, and 29 respectively and use FCFS to schedule the execution. 


Required information:

  1. Draw the Gantt chart showing the execution of the CPU.
  2. What is the CPU utilization?
  3. What is the system’s throughput (in process /ms)?
  4. What is the average turnaround time of all the processes?
  5. What is the average waiting time of all the processes?
1
Expert's answer
2021-10-25T00:05:08-0400
Dear sfghjlad, your question requires a lot of work, which neither of our experts is ready to perform for free. We advise you to convert it to a fully qualified order and we will try to help you. Please click the link below to proceed: Submit order

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS