6.
ACTIVITY PRECEDENCE DURATION (IN
DAYS)
A NONE 3
B A 12
C NONE 6
D B 1
E C, D 2
F E 1
G F 6
H F 3
I F 1
J G 3
K H, I, J 10
L K 2
M L 2
REQUIRED:
1. CONSTRUCT THE NETWORK DIAGRAM USING AON.
2. LIST ALL THE PATHS OF THE NETWORK AND THEIR RESPECTIVE DURATION.
3. IDENTIFY THE CRITICAL PATH/S AND ITS DURATION.
4. COMPUTE THE SLACK TIME FOR EACH ACTIVITY.
5. IDENTIFY THE CRITICAL AND THE NON-CRITICAL ACTIVITIES.