Spiral model has four quadrants.
Quadrant 1 - Determine objectives, alternatives and constraints:
- Objectives − Functionality, performance, hardware/software interface, critical success factors, etc.
- Alternatives − Build, reuse, buy, sub-contract, etc.
- Constraints − Cost, schedule, interface, etc.
Quadrant 2 - Evaluate alternatives, identify and resolve risks:
- Study alternatives relative to the objectives and constraints that are determined.
- Identify risks such as lack of experience, new technology, tight schedules, etc.
- Resolve the identified risks evaluating their impact on the project, identifying the needed mitigation and contingency plans and implementing them. Risks always need to be monitored.
Quadrant 3 - Develop next-level product:
Typical activities include −
- Create a design
- Review design
- Develop code
- Inspect code
- Test product
Quadrant 4 - Plan next phase:
Typical activities include −
- Develop project plan
- Develop configuration management plan
- Develop a test plan
- Develop an installation plan