Answer to Question #173059 in Statistics and Probability for Johb

Question #173059

 The time taken to complete a particular type of a job is distributed approximately normally with mean 1.8 and standard deviation of 0.1hours.

Given that ‘’normal-time’’ work ends at 6pm and a job is started at 4.00pm, determine the probability that the job will need overtime.                         (2marks)

Calculate the estimated completion time (to the nearest minute) that should be set so that there is a 90% chance that the job is completed on time.                 (3marks)

 


1
Expert's answer
2021-03-22T10:57:53-0400

Given "\\mu=1.8, \\sigma=0.1"


"P(X>2)=1-P(X\\leq2)"

"=1-P(Z\\leq\\dfrac{2-1.8}{0.1})=1-P(Z\\leq2)"

"\\approx0.02275"

"P(X<x)=P(Z<\\dfrac{x-1.8}{0.1})=0.9"

"\\dfrac{x-1.8}{0.1}\\approx1.645"

"x=1hr\\ 58\\ min"

The estimated completion time is 5.58 pm.



Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
APPROVED BY CLIENTS