Question #157270

A contractor estimates the probabilities for the number of days required to complete a certain type of project as follows:



Time (days) 1 2 3 4 5


Probability 0.04 0.21 0.34 0.31 0.10


(1) what is the probability that a randomly chosen project will take less than 3 days to complete?

(2) Find the expected time to complete a project.

(3) Find the standard deviation of time required to complete a project.

(If the contractor's project cost is made up of two parts: a fixed cost of $100 million plus $10 million for each day taken to complete the project, find the variance of total project costs.



Expert's answer

(1) The probability that a randomly chosen project will take less than 3 days to complete is equal

p1+p2 = 0.04+0.21 = 0.25


(2) The expected time to complete a project is equal

E[X]=p1+2p2+3p3+4p4+5p5E[X] = p_1+2p_2+3p_3+4p_4+5p_5

E[X]=0.04+20.21+30.34+40.31+50.1=3.22E[X] = 0.04 + 2\cdot 0.21 +3\cdot 0.34 +4\cdot0.31 + 5\cdot0.1 = 3.22


(3) E[X2]=p1+22p2+32p3+42p4+52p5E[X^2] = p_1+2^2p_2+3^2p_3+4^2p_4+5^2p_5

E[X2]=0.04+40.21+90.34+160.31+250.1=11.4E[X^2] = 0.04 + 4\cdot 0.21 +9\cdot 0.34 +16\cdot0.31 + 25\cdot0.1 = 11.4

Var[X]=E[X2]E[X]2Var[X] = E[X^2] - E[X]^2

Var[X]=11.43.222=1.0316Var[X] = 11.4 - 3.22^2 = 1.0316

The standard deviation of time required to complete a project is equal

σX=Var[X]=1.0316=1.0157\sigma_X=\sqrt{Var[X]} = \sqrt{1.0316} = 1.0157


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

LATEST TUTORIALS
APPROVED BY CLIENTS