A contractor estimates the probabilities for the number of days required to complete a certain type of project as follows:
Time (days) 1 2 3 4 5
Probability 0.04 0.21 0.34 0.31 0.10
(1) what is the probability that a randomly chosen project will take less than 3 days to complete?
(2) Find the expected time to complete a project.
(3) Find the standard deviation of time required to complete a project.
(If the contractor's project cost is made up of two parts: a fixed cost of $100 million plus $10 million for each day taken to complete the project, find the variance of total project costs.
(1) The probability that a randomly chosen project will take less than 3 days to complete is equal
p1+p2 = 0.04+0.21 = 0.25
(2) The expected time to complete a project is equal
(3)
The standard deviation of time required to complete a project is equal