Olive Construction Company is determining whether it should submit a bid for a new shopping center. In the past, Olive's main competitor, Base Construction Company, has submitted bids 70% of the time. If Base Construction Company does not bid on a job, the probability that Olive Construction Company will get the job is 0.50. If Base Construction Company does bid on a job, the probability that Olive Construction Company will get the job is 0.25.

(a)Draw the tree diagram



1
Expert's answer
2021-01-21T19:58:26-0500

Let's denote BB  for Base Construction Company submits bids on a job and OO for Olive Construction Company getting the job.

Thus here we have:

P(B)=0.70P(B)=0.70

P(Bˉ)=1P(B)=10.70=0.30P(\bar{B})=1-P(B)=1-0.70=0.30

P(OB)=0.25P(O|B)=0.25

P(OBˉ)=0.50P(O|\bar{B})=0.50


P(OB)=P(OB)P(B)=0.25(0.7)=0.175P(O\cap B)=P(O|B)P(B)=0.25(0.7)=0.175

P(OBˉ)=P(OBˉ)P(Bˉ)=0.50(0.3)=0.150P(O\cap\bar{B})=P(O|\bar{B})P(\bar{B})=0.50(0.3)=0.150

Probability Table:


BBˉO0.1750.1500.325Oˉ0.5250.1500.6750.7000.3001\def\arraystretch{1.5} \begin{array}{c:c:c:c} & B & \bar{B}& \\ \hline O & 0.175 & 0.150 & 0.325\\ \hdashline \bar{O} & 0.525 & 0.150 & 0.675 \\ \hdashline & 0.700 & 0.300 & 1 \end{array}

Venn diagram




Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment