Olive Construction Company is determining whether it should submit a bid for a new shopping center. In the past, Olive's main competitor, Base Construction Company, has submitted bids 70% of the time. If Base Construction Company does not bid on a job, the probability that Olive Construction Company will get the job is 0.50. If Base Construction Company does bid on a job, the probability that Olive Construction Company will get the job is 0.25.
(a)Draw the tree diagram
Let's denote for Base Construction Company submits bids on a job and for Olive Construction Company getting the job.
Thus here we have:
Probability Table:
Venn diagram