An established company has decided to add a new product to its line. It will buy the product from a manufacturing concern, package it, and sell it to a number of distributors selected on a geographical basis. List of activities involved in the new product introduction and their immediate predecessors are shown in the following table (4 points). Activity Preceding Actives Activity duration (Days) A --- 4 B --- 7 C --- 6 D A, B 5 E A, B 7 F C, D, E 6 G C, D, E 5 a. Draw the project network using the Activity on Arrow (A-O-A) convention. b. Compute float (slack) time of each activity. c. Determine the critical path and calculate the project duration (completion time)
1
Expert's answer
2021-10-28T15:05:28-0400
(a)The project network will be as shown below;
(b)Slack time for each activity will be as calculated below.
"assignmentexpert.com" is professional group of people in Math subjects! They did assignments in very high level of mathematical modelling in the best quality. Thanks a lot
Comments