Question #261241

QUESTION 2 (TOPIC: OVERHEAD COSTING)



Given: Total budgeted overheads = Shs.240, 000 and the Production budget is given as follows:


Product A B


i) Units 20,000 10,000


ii) Labour hours 20,000 20,000


iii) Labour cost Shs.17,500 Shs.22,500


iv) Machine hours 45,000 15,000


v) Material cost Shs.15,000 Shs.25,000



Required;


The overhead absorption rate per unit of A and B using the following methods:


a) Unit method


b) Percentage on material cost.


c) Percentage on labour cost.


d) Percentage On prime cost.


e) Labour hour rate.


f) Machine hour rate.


Expert's answer

a) Unit method


overhead absorption rate= TotalbudgetedoverheadsUnits\frac{Total budgeted overheads}{Units}


Of A: =Shs240,00020,000=Shs\frac{Shs240,000}{20,000}=Shs. 12 per unit of B: =Shs240,00010,000=Shs\frac{Shs240,000}{10,000}=Shs. 24 per unit



b) Percentage on material cost.


overhead absorption rate= TotalbudgetedoverheadsMaterialcosts\frac{Total budgeted overheads}{Material costs}



Of A: =Shs240,00015,000×100%=1600%\frac{Shs240,000}{15,000}\times100\%=1600\% Of B: =Shs240,00025,000×100%=960%\frac{Shs240,000}{25,000}\times100\%=960\%



c) Percentage on labour cost.


overhead absorption rate= TotalbudgetedoverheadsLabourcosts\frac{Total budgeted overheads}{Labourcosts}



Of A: =Shs240,00017,500×100%=1371.43%\frac{Shs240,000}{17,500}\times100\%=1371.43\% Of B: =Shs240,00022,500×100%=1066.67%\frac{Shs240,000}{22,500}\times100\%=1066.67\%


d) Percentage On prime cost.


overhead absorption rate= TotalbudgetedoverheadsPrimecosts\frac{Total budgeted overheads}{Primecosts}


Of A: =Shs240,00032,500×100%=738.46%\frac{Shs240,000}{32,500}\times100\%=738.46\% Of B: =Shs240,00047,500×100%=505.26%\frac{Shs240,000}{47,500}\times100\%=505.26\%


e) Labour hour rate.


overhead absorption rate= Totalbudgetedoverheadslabourhours\frac{Total budgeted overheads}{labour hours}


Of A: =Shs240,00020,000=Shs\frac{Shs240,000}{20,000}=Shs. 12 per unit Of B: =Shs240,00020,000=Shs\frac{Shs240,000}{20,000}=Shs. 12 per unit


f) Machine hour rate.


overhead absorption rate= Totalbudgetedoverheadsmachinehours\frac{Total budgeted overheads}{machine hours}


Of A: =Shs240,00045,000=Shs\frac{Shs240,000}{45,000}=Shs. 5.33 per machine hour Of B =Shs240,00015,000=Shs\frac{Shs240,000}{15,000}=Shs. 16 per machine hour









Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

LATEST TUTORIALS
APPROVED BY CLIENTS