Question #57603

25 builders have completed 1/5 of a build in 8 days. The project leader then decides that the build now must be completed in 20 days . What is the smallest number of additional builders the project leader must hire to complete the build within the new schedule ?

Expert's answer

Answer on Question #57603 – Math – Algebra

Condition

25 builders have completed 1/5 of a build in 8 days. The project leader then decides that the build now must be completed in 20 days. What is the smallest number of additional builders the project leader must hire to complete the build within the new schedule?

Solution

For time we will use constant tt variable. For final amount of builders we will use xx variable. Builders have completed 1/5 of a build, so they must build 4/5 of a build. We spent 8 days for building and we should finish project in 20 days, so we have 12 days to finish it.

We can build system of equations:


{258t=1/5x12t=4/5\left\{ \begin{array}{l} 25 \cdot 8t = 1/5 \\ x \cdot 12t = 4/5 \end{array} \right.8t=151258t = \frac{1}{5} \cdot \frac{1}{25}8t=11258t = \frac{1}{125}t=11258=11000t = \frac{1}{125 \cdot 8} = \frac{1}{1000}


We put tt value to second equation and try to find xx:


x1211000=45x \cdot 12 \cdot \frac{1}{1000} = \frac{4}{5}x=41000512=400667 buildersx = \frac{4 \cdot 1000}{5 \cdot 12} = \frac{400}{6} \approx 67 \text{ builders}

6725=4267 - 25 = 42 builders

So, the project leader must hire 42 builders to complete the build within the new schedule.

Answer

42 people

www.AssignmentExpert.com


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

LATEST TUTORIALS
APPROVED BY CLIENTS