a tool will cut for 6 hours before it needed sharpening it takes 20 minutes to change the tool if the tool can be sharpened 12 times before it is discarded determine the unit tool change time per cycle"
6 hour 20 minutes to be sharpened once
380 minutes = sharpened once
(12) 380 minutes = sharpened twelve times
4560 minutes = sharpened 12 times
4560/60 = 76 hours
"\\therefore" The unit tool change time per cycle is 76 hours per cycle.