Following information has been extracted from costing record of Abdul Engineering works in respect of Job No. 101.
Material Rs.5,800
Wages:
Department A 100 hours @ Rs. 5 per hour
Department B 200 hours @ Rs. 3 per hour
Overhead for the two department are estimated as follows:
Variable Overhead
Department A Rs.10,000 for 5,000 direct labour hours
Department B Rs.30,000 for 10,000 direct labour hours
Fixed Overheads: Estimated at Rs.50,000 for 50,000 normal working hours.
Required:
Calculate the cost of Job No. 101 and calculate the price to be charged so as to given a profit of 20% on selling price.