Question #165431

Suppose you have a budgeted cost of a project at PKR 100,000,000. The project is to be completed in 12 months. After a month, you have completed 5 percent of the project at a total expense of 1,000,000. The planned completion should have been 10 percent.Using the project status calculate PV, EV, AC, BAC, CV, SPI and CPI.


Expert's answer

BAC 100,000,000

PV 10,000,000

EV 5,000,000

AC 1,000,000

CV 4,000,000

CPI 5

SPI 0.5


Explanation:

BAC = Budgeted cost of the project = 100,000,000

 

PV = Planned value = Planned completion percent x BAC = 10% x 10000000 = 0.10 x 100000000=10000000

 

EV = Earned value = Actual completion percent x BAC = 5% x 100,000000 = 0.05 x 100000000 = 5000000

 

AC = Actual cost incurred in the project = 1,000,000

 

CV = Cost Variance = EV - AC = 5000000 - 1000000= 4000000

 

CPI = Cost Performance Index = EV / AC = 5000000 / 1000000 = 5

 

SPI = Schedule Performance Index = EV / PV = 5000000 / 10000000 = 0.5

 

 

 

 



Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

LATEST TUTORIALS
APPROVED BY CLIENTS