SOLUTION TO QUESTION Q149858
COST SHEET JOB NUMBER NO 303
Direct materials Sh. 41,100
Add wages: Department
A =60 hrs*Sh. 300/hr= Sh. 18,000
B =40hrs*Sh. 200/hr= Sh. 8,000
C=20hrs*Sh.50/hr= Sh. 1,000
Total wages Sh. 27,000
Prime cost(Direct material+Wages) Sh. 68,100
Add Overhead variables: Department
A =60 hrs*Sh. 10/hr= Sh. 600
B =40hrs*Sh. 20/hr= Sh. 800
C=20hrs*Sh.40/hr= Sh. 800
Total overhead costs Sh. 2,200
Fixed costs overhead (60+40+20)*Sh. 20/hr Sh. 2,400
Total job cost Sh. 72,700