Which step Of SDLC performs cost-benefit analysis?
A Feasibility Study.
B Analysis.
C Design.
D None of the above.

Expert's answer

(A) Feasibility study

phase one of the SDLC involves the project preliminary and the determination of project viability is in this phase that cost-benefit evaluation is done and submission for the preliminary plan and recommendations. hence (A) Feasibility study is the correct answer to the quiz.