Question #51059

How much work is done when a bucket of mass 1.5 kg with 10 kg of water in it is pulled up from the bottom of a well 8
m deep? Take g = 9:8m/s2
1

Expert's answer

2015-03-11T06:08:30-0400

Answer on Question 51059, Physics, Mechanics | Kinematics | Dynamics

Question:

How much work is done when a bucket of mass 1.5kg1.5kg with 10kg10kg of water in it is pulled up from the bottom of a well 8m8m deep? Take g=9.8ms2g = 9.8\frac{m}{s^2}

Solution:

By the definition, work done by the bucket of mass 1.5kg1.5kg with 10kg10kg of water in it if it is pulled up from the bottom of a well 8m8m deep is:


W=(mbucket+mwater)gh=(1.5kg+10kg)9.8ms28m=901.6J.W = (m_{bucket} + m_{water})gh = (1.5kg + 10kg) \cdot 9.8\frac{m}{s^2} \cdot 8m = 901.6J.


Answer:


W=901.6J.W = 901.6J.


http://www.AssignmentExpert.com/


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!