1. Sand falls at the rate of 0.15kg/s on a conveyor belt moving horizontally at a constant speed of 2 m/s , calculate i) the extra force necessary to maintain this speed ii) the rate at which work is done by this force, iii) the change in kinetic energy per second of the sand on the belt. Account for the difference between answer to (ii) to (iii)
1

Expert's answer

2013-08-07T09:09:00-0400

1. Sand falls at the rate of 0.15kg/s0.15\mathrm{kg / s} on a conveyor belt moving horizontally at a constant speed of 2 m/s, calculate i) the extra force necessary to maintain this speed ii) the rate at which work is done by this force, iii) the change in kinetic energy per second of the sand on the belt. Account for the difference between answer to (ii) to (iii)



Solution

Let ll - Length of conveyor belt, γ=0.15kg/s\gamma = 0.15 \, kg/s - conveyor's productivity,

vc2m/sv_{c} - 2m / s - conveyor's belt speed.

Let's define the mass of sand on a conveyor. Calculate the time in which the sand will run from the beginning to the end conveyor


l=vctt=lvcms=γt=lvcγl = v _ {c} t \rightarrow t = \frac {l}{v _ {c}} \rightarrow m _ {s} = \gamma t = \frac {l}{v _ {c}} \gamma


Suppose that the conveyor belt has no weight. Then, to move the entire mass of sand evenly on the assembly line requires strength


Fextra=msg=lvcγgF _ {e x t r a} = m _ {s} g = \frac {l}{v _ {c}} \gamma g


Work done this force A=Fextral=l2vcγg\rightarrow A = F_{extra}l = \frac{l^2}{v_c}\gamma g

The change in kinetic energy per second of the sand on the belt is Zero

Answers:

i. Fextra=lvcγgF_{extra} = \frac{l}{v_c}\gamma g

ii. A=l2vcγgA = \frac{l^2}{v_c}\gamma g

iii. 0

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!
LATEST TUTORIALS
APPROVED BY CLIENTS