The construction of a building may be delayed by a strike. Suppose that the
probability that there will be a strike is 0.70, the probability that the construction
will be completed on time if there is no strike is 0.90 and the probability that the
building will be completed on time if there is a strike is 0.40, what is the
probability that the construction will be completed on time.
1
Expert's answer
2017-02-24T15:41:05-0500
P(A) is the probability that the construction will be completed on time; P(H1)is the probability that there will be a strike; P(H2) is the probability that there will not be a strike; P(H1/A) is the probability that the construction will be completed on time if there is no strike; P(H2/A) is the probability that the building will be completed on time if there is a strike.
By the condition of the problem we have that P(H1) = 0.70, P(H2) = 1 - P(H1) = 1 - 0.70 = 0.30, P(H1/A) = 0.90, P(H2/A) = 0.40.
Numbers and figures are an essential part of our world, necessary for almost everything we do every day. As important…
APPROVED BY CLIENTS
Finding a professional expert in "partial differential equations" in the advanced level is difficult.
You can find this expert in "Assignmentexpert.com" with confidence.
Exceptional experts! I appreciate your help. God bless you!
Comments
Leave a comment