Question #3159

Place the steps below in the correct order for the construction of a control chart.

I. Compute control limits.
II. Measure the quality characteristic of interest.
III. Record the data.
IV. Gather samples of data of uniform size.
V. Chart the control limits.

Expert's answer

1. & Gather samples of data of uniform size.
2. & Measure the quality characteristic of interest.
3. Record the data.
4. Compute control limits.
5. Chart the control limits.