Place the steps below in the correct order for the construction of a control chart.
I. Compute control limits.
II. Measure the quality characteristic of interest.
III. Record the data.
IV. Gather samples of data of uniform size.
V. Chart the control limits.
1
Expert's answer
2011-06-20T12:25:07-0400
1. & Gather samples of data of uniform size. 2. & Measure the quality characteristic of interest. 3. Record the data. 4. Compute control limits. 5. Chart the control limits.