1.2 It has been established that completion of construction projects can be delayed because of
unfavourable weather conditions. The probabilities are 0.6 that there will be unfavourable
weather, and 0.85 that the construction project will be completed on time if the weather is
favourable and 0.35 that the construction project will be completed on time if there is
unfavourable weather.
Required:
What is the probability that the construction project will not be completed on time? (10)
Question II [25]
Solution:
Notations:
U = unfavourable weather
F = favourable weather
C = work completed
Given, P(U) = 0.6, P(C|F) = 0.85, P(C|U) = 0.35
So, P(C) = 1-0.6 = 0.4
Now, P(C) = P(U)P(C|U) + P(F)P(C|F) = 0.6 x 0.35 + 0.4 x 0.85 = 0.55
Then, P(C') = 1-P(C) = 1-0.55 = 0.45