Question #47102

A book binder has one printing press, one binding machine and manuscripts of seven
different books. The time required for performing printing and binding operations for
different printing and binding operations for different books are shown below:

Book 1 2 3 4 5 6 7

Printing Time 20 90 80 20 120 15 65
(Days)

Binding Time 25 60 75 30 90 35 50
(Days)

Find the optimum sequence of processing of the jobs that minimises the total time required.
Also compute the optimal time required.
1

Expert's answer

2014-09-30T09:20:46-0400

Answer on Question #47102 – Math - Algorithms | Quantitative Methods

A book binder has one printing press, one binding machine and manuscripts of seven different books. The time required for performing printing and binding operations for different printing and binding operations for different books are shown below:

Book 1 2 3 4 5 6 7

Printing Time (Days) 20 90 80 20 120 15 65

Binding Time (Days) 25 60 75 30 90 35 50

Find the optimum sequence of processing of the jobs that minimises the total time required. Also compute the optimal time required.

Solution

Step 1. Minimum time is 15 days on printing press (M1)(M_1) for job 6 so it will be sequenced earlier as shown



Step II. Now book 1 and 4 have the least time of 20 days on printing press (M1)(M_1) so these two books will be sequenced as



Step III. After eliminating job 6, 1 and 4 least time is for job 7 on binding machine (M2)(M_2) so it will be placed last in the sequence.



Step IV. Now book 2 has least time of 60 on M2M_2, hence it will be placed at the end.



Step V. Book 3 has the least time of 75 days on M2M_2 so it will be placed as below.



Step VI. Jobs 5 will be placed in the vacant place



Step VII. Total processing time can be calculated as follow:



**Total idle time**

Printing = (460 - 410) = 50 days as the printing of last job (7) is finished on 410 days but binding finishes only after 460 days, so printing machine is idle for 50 days.

Binding = 15 + 70 + 5 + 5 = 95 days

www.AssignmentExpert.com


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

Assignment Expert
15.07.21, 22:56

Dear Yuvraj, please use the panel for submitting a new question.


Yuvraj
16.06.21, 07:59

Jai Hind Industry uses MRP for its material planning. The table below provides the information about a particular component Z. The demand for this component is uncertain and in order to take care of the sudden spurt in the demand, a safety stock of 100 items if recommended. Week Weeks 1 2 3 4 5 6 7 Requi reme 50 nts 100 80 200 50 40 100 Order Quantity 300 on hand stock 300 2 weeks

LATEST TUTORIALS
APPROVED BY CLIENTS