Question #56576

(b) A company is involved in the production of two items (X and Y). The resources need to produce X and Y are twofold, namely machine time for automatic processing and craftsman time for hand finishing. The table below gives the number of minutes required for each item:

Machine time Craftsman time
Item X 13 20
Item Y 19 29

The company has 40 hours of machine time available in the next working week but only 35 hours of craftsman time. Machine time is costed at £10 per hour worked and craftsman time is costed at £2 per hour worked. Both machine and craftsman idle times incur no costs. The revenue received for each item produced (all production is sold) is £20 for X and £30 for Y. The company has a specific contract to produce 10 items of X per week for a particular customer. Formulate the problem of deciding how much to produce per week as a linear program hence make the decision.

Expert's answer

Answer on Question #56576 – Math – Other

A company is involved in the production of two items (X and Y). The resources need to produce X and Y are twofold, namely machine time for automatic processing and craftsman time for hand finishing. The table below gives the number of minutes required for each item:



The company has 40 hours of machine time available in the next working week but only 35 hours of craftsman time. Machine time is costed at £10 per hour worked and craftsman time is costed at £2 per hour worked. Both machine and craftsman idle times incur no costs. The revenue received for each item produced (all production is sold) is £20 for X and £30 for Y. The company has a specific contract to produce 10 items of X per week for a particular customer. Formulate the problem of deciding how much to produce per week as a linear program hence make the decision.

Solution

Let xx be the number of items of XX, yy be the number of items of YY.

Then the LP is

maximise


20x+30y10(machine time worked)2(craftsman time worked)20x + 30y - 10(\text{machine time worked}) - 2(\text{craftsman time worked})


subject to:


13x+19y40(60) machine time13x + 19y \leq 40(60) \text{ machine time}20x+29y35(60) craftsman time20x + 29y \leq 35(60) \text{ craftsman time}x10 contractx \geq 10 \text{ contract}x,y0x, y \geq 0


so that the objective function becomes

maximise


20x+30y10(13x+19y)602(20x+29y)6020x + 30y - \frac{10(13x + 19y)}{60} - \frac{2(20x + 29y)}{60}


i.e. maximise


17.1667x+25.8667y17.1667x + 25.8667y


subject to:


13x+19y240013x + 19y \leq 240020x+29y210020x + 29y \leq 2100x10x \geq 10


x,y\geq 0

It is plain from the diagram below that the maximum occurs at the intersection of x=10x = 10 and

20x+29y210020x + 29y\leq 2100

Solving simultaneously, rather than by reading values off the graph, we have that x=10x = 10 and y=65.52y = 65.52 with the value of the objective function being £1866.5.



www.AssignmentExpert.com


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

LATEST TUTORIALS
APPROVED BY CLIENTS