Question #166293

The number of men needed to cement a barangay road vanes directly with the length of the road at a constant

width and inversely with the number of days required to do the job. If a 30m road can be cemented by 10 men in

12 days how wide is the road? How many days will it take 50 men to cement a road that is 1 km long?


1
Expert's answer
2021-02-24T06:05:06-0500

Let N=N= the number of men needed, L=L= the length of the road, and

t=t= the number of days required to do the job. Then


N=kLtN=k\cdot \dfrac{L}{t}

Given N1=10,L1=30 m,t1=12 days,N_1=10, L_1=30\ m, t_1=12\ days,

N2=50,L2=1 km=1000 mN_2=50, L_2=1\ km=1000\ m

Find t2t_2


N2N1=kL2t2kL1t1\dfrac{N_2}{N_1}=\dfrac{k\cdot \dfrac{L_2}{t_2}}{k\cdot \dfrac{L_1}{t_1}}

N2L1t1=N1L2t2N_2\cdot\dfrac{L_1}{t_1}=N_1\cdot\dfrac{L_2}{t_2}

t2=t1N1L2N2L1t_2=t_1\cdot\dfrac{N_1\cdot L_2}{N_2\cdot L_1}

t2=121010005030=80(days)t_2=12\cdot\dfrac{10\cdot 1000}{50\cdot 30}=80(days)

A 1 km road can be cemented by 50 men in 80 days.



Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!
LATEST TUTORIALS
APPROVED BY CLIENTS