The number of men needed to cement a barangay road vanes directly with the length of the road at a constant
width and inversely with the number of days required to do the job. If a 30m road can be cemented by 10 men in
12 days how wide is the road? How many days will it take 50 men to cement a road that is 1 km long?
Let "N=" the number of men needed, "L=" the length of the road, and
"t=" the number of days required to do the job. Then
Given "N_1=10, L_1=30\\ m, t_1=12\\ days,"
"N_2=50, L_2=1\\ km=1000\\ m"
Find "t_2"
"N_2\\cdot\\dfrac{L_1}{t_1}=N_1\\cdot\\dfrac{L_2}{t_2}"
"t_2=t_1\\cdot\\dfrac{N_1\\cdot L_2}{N_2\\cdot L_1}"
"t_2=12\\cdot\\dfrac{10\\cdot 1000}{50\\cdot 30}=80(days)"
A 1 km road can be cemented by 50 men in 80 days.