Operations Research Answers

Questions: 623

Answers by our Experts: 472

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Search & Filtering

Use simplex method to maximize 𝑓 = 3π‘₯ + 5𝑦 + 4𝑧 subject to the conditions 2π‘₯ + 3𝑦 ≀ 18 2π‘₯ + 5𝑦 ≀ 10 3π‘₯ + 2𝑦 + 4𝑧 ≀ 15 and π‘₯, 𝑦, 𝑧 β‰₯ 0.


A company has fixed funds to undertake three projects through contractors. Five contractors have already applied to do the job and each has submitted a quotation for each project from which the company has estimated the saving associated with allocating a given project to a specific contractor. The figures are given in the table below and the company’s policy is to give one project per contractor

. Project

Contractor 1 2 3

A 1020 1080 1050

B 1500 1410 1050

C 1110 750 1050

D 1080 1020 1080

E 1470 1290 1590

Determine who should be assigned which project and the maximum saving the company can make.


) Five applicants are competing for four jobs . The scores from aptitude tests related to the four vacancies are given below. It is believed the tests measure an applicant possible performance in the job.

JOBS

APPLICANTS 1 2 3 4

A 18 15 12 25

B 9 11 10 15

C 12 10 14 16

D 9 10 10 21

E 14 18 26 26

Determine who should be assigned which job in order to maximize overall output


A company has 5 salesmen and 5 customers to attend to on a particular day. The company has estimated the savings in dollars associated with assigning a particular salesman to a specific client. These estimates are as given in the table below

Clients

1 2 3 4 5

A 30 37 40 28 40

Salesmen B 40 24 27 21 36

C 40 32 33 30 35

D 25 38 40 36 36

E 29 62 41 34 39

Determine who should be assigned which client and the maximum profit the company can achieve from the allocations


A small project is composed of 8 activities whose time estimates are listed below

Activity Time in weeks

i j Optimistic(a) Most likely(M) Pessimistic(b)

A 1 2 2 5 8

B 2 3 4 7 10

C 2 4 4 9 11

D 3 5 6 10 20

E 4 6 1 3 5

F 4 5 3 6 9

G 5 7 4 5 12

H 6 7 6 8 10

i) Develop a PERT network for the project .

ii) Determine the expected value and the variance for every activity.

iii) Calculate EST and LCT for every node.

iv) Find the critical path for the project .

v) Compute the probability of completing the project in 36 weeks .


A small project is composed of 7 activities whose time estimates in weeks are listed below:

Activity Predecessors Optimistic Most likely Pessimistic

A - 1 2 4

B - 5 6 7

C - 2 4 5

D A 1 3 4

E C 4 5 7

F A 3 4 5

G B,D,E 1 2 3

i) Draw the network.

ii) Calculate the expected duration and variance of every task.

iii) Determine the critical path.

iv) Calculate the expected project duration and the variance of the project duration based on network analysis.

v) Calculate the probability that the project will be completed on or before a deadline of 10 weeks


Β A small project is composed of seven activities whose time estimates in hours are given below.

Activity 1-2 1-3 1-4 2-5 3-5 4-6 5-6

a 1 1 2 1 2 2 3

b 7 7 8 1 14 8 15

M 1 4 2 1 5 5 6

a=optimistic time. b=pessimistic time M=Most likely time.

i) Draw the project network.

ii) Find the expected duration and variance of each activity.

iii) Determine the critical path.

iv) Find the expected project completion time.

v) Calculate the probability that the project will be completed three weeks earlier than expected.

vi) If the project’s due date is 18 weeks, find the probability of not meeting the due date.


. A tailor has the following material available: 16 sq. yd. cotton, 11 sq. yd. silk and 15 sq. yd. wool. A suit requires 2 sq. yd. cotton, 1 sq. yd. silk and 1 sq. yd. wool. A gown requires 1 sq. yd. cotton, 2 sq. td. Silk and 3 sq. yd. wool. If a suit sells for Rs. 300/- and a gown for Rs. 500/-, how many of each garment should the tailor mak to obtain the maximum amount of profit?


Β Explain ways in which the CPM type of networks differ from PERT networksΒ 


Β Solve the following linear programming problem using the simplex method.

π‘€π‘–π‘›π‘–π‘šπ‘–π‘§π‘’ 𝑃 = 2100𝑦1 + 2400𝑦2 + 10𝑦3 βˆ’ 70𝑦4

𝑠𝑒𝑏𝑗𝑒𝑐𝑑 π‘‘π‘œ

25𝑦1 + 15𝑦2 + 𝑦3 β‰₯ 250

20𝑦1 + 30𝑦2 βˆ’ 𝑦3 βˆ’ 𝑦4 β‰₯ 300

𝑦1 β‰₯ 0, 𝑦2 β‰₯ 0, 𝑦3 β‰₯ 0 , 𝑦4 β‰₯ 0Β 


LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS