Answer to Question #332002 in Operations Research for Zara

Question #332002

Embolot construction project consists of the following activities with duration in weeks of each activity given in brackets. A(8), B(7) and C(10) can be executed concurrently. A and B precede D(3). B precedes E(1) and F(9). F and C precede G(5) and H(7). E and G precede J(3). H precedes K(3). D, J and K precede L(4). L is the terminating activity in the project.

a)     Construct the precedence table and hence draw the network diagram for the project.


0
Expert's answer

Answer in progress...

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS