Embolot construction project consists of the following activities with duration in weeks of each activity given in brackets. A(8), B(7) and C(10) can be executed concurrently. A and B precede D(3). B precedes E(1) and F(9). F and C precede G(5) and H(7). E and G precede J(3). H precedes K(3). D, J and K precede L(4). L is the terminating activity in the project.
a) Construct the precedence table and hence draw the network diagram for the project.