The Hardrock Concrete Company has plants in three locations and is currently working on three major construction projects, each located at a different site. The shipping cost per truckload of concrete, daily plant capacities, and daily project requirements are provided in the accompanying table.

Formulate an initial feasible solution to Hardrock’s transportation problem using Vogel’s Approximation Method.


1
Expert's answer
2021-11-10T09:02:41-0500

Question is incomplete.

Complete question is:

John, president of Hardrock Concrete Company, has plants in three

locations and is currently working on three major construction projects, located at

different sites. The shipping cost per truckload of concrete, plant capacities, and

project requirements are provided in the following table.

"\\begin{matrix}\n & project A & project B & project C & plant \\space capacities \\\\\n plant 1 & \\$10 & \\$4 & \\$ 11 & 70\\\\\n plant 2& \\$12 & \\$5 & \\$ 8 & 50\\\\\n plant 3 & \\$9 & \\$7 & \\$6 & 30\\\\\nProject \\space requirements & 40 & 50 & 60 & 150\n\\end{matrix}"

Formulate an initial feasible solution to Hardrock’s transportation problem using Vogel’s Approximation Method.


Solution:


(I)The rim values for plant 1=70 and project A=40 are compared.

The smaller of the two i.e. min(70,40) = 40 is assigned to plant 1 project A

This meets the complete demand of project A and leaves 70 - 40=30 units with plant 1.

(II)The rim values for plant1=30 and project B=50 are compared.

The smaller of the two i.e. min(30,50) = 30 is assigned to plant1 project B

This exhausts the capacity of plant1 and leaves 50 - 30=20 units with project B

(III)The rim values for plant2=50 and project B=20 are compared.

The smaller of the two i.e. min(50,20) = 20 is assigned to plant2 project B

This meets the complete demand of project B and leaves 50 - 20=30 units with plant2

(IV)The rim values for plant2=30 and project C=60 are compared.

The smaller of the two i.e. min(30,60) = 30 is assigned to plant2 project C

This exhausts the capacity of plant2 and leaves 60 - 30=30 units with project C

(V)The rim values for plant3=30 and project C=30 are compared.

The smaller of the two i.e. min(30,30) = 30 is assigned to plant3 project C


Initial feasible solution is

"\\begin{matrix}\n & project A & project B & project C & plant \\space capacities \\\\\n plant 1 & 10(40) & 4(30) & 11 & 70\\\\\n plant 2& 12 & 5(20) & 8 (30)& 50\\\\\n plant 3 & 9 & 7 & 6(30) & 30\\\\\nProject \\space requirements & 40 & 50 & 60 & 150\n\\end{matrix}"

The minimum total transportation cost =10×40+4×30+5×20+8×30+6×30=1040


Here, the number of allocated cells = 5 is equal to m + n - 1 = 3 + 3 - 1 = 5

∴ This solution is non-degenerate



Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS