Answer to Question #258499 in Operations Research for Manjeet

Question #258499

Solve the following job sequencing problem by giving an optimal sequence of jobs, and find the



total elapsed time also. Note that M1, M2, M3, M4, M5 and M6 are machines and A, B, C, D



are jobs.



Jobs → A B C D



M1 20 19 13 22



M2 10 8 7 6



M3 9 11 10 5



Machines M4 4 8 7 6



M5 12 10 9 10



M6 27 21 17 14

1
Expert's answer
2021-11-01T16:58:11-0400

An optimal solution to this problem can be obtained, if either or both of the following conditions hold(s):

"min\\ t_{1j}\\ge max\\ t_{ij}"

"min\\ t_{mj}\\ge max\\ t_{ij}"

for i=2,3, ..., m-1


We have:

"min\\ t_{1j}= t_{13}=13"

"max\\ t_{ij}=\\ t_{61}=27"

"min\\ t_{1j}<max\\ t_{ij}"


"min\\ t_{mj}= t_{64}=14"

"min\\ t_{mj}< max\\ t_{ij}"


So, optimal solution to this problem cannot be obtained.


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS