Question #258499

Solve the following job sequencing problem by giving an optimal sequence of jobs, and find the



total elapsed time also. Note that M1, M2, M3, M4, M5 and M6 are machines and A, B, C, D



are jobs.



Jobs → A B C D



M1 20 19 13 22



M2 10 8 7 6



M3 9 11 10 5



Machines M4 4 8 7 6



M5 12 10 9 10



M6 27 21 17 14

Expert's answer

An optimal solution to this problem can be obtained, if either or both of the following conditions hold(s):

min t1j≥max tijmin\ t_{1j}\ge max\ t_{ij}

min tmj≥max tijmin\ t_{mj}\ge max\ t_{ij}

for i=2,3, ..., m-1


We have:

min t1j=t13=13min\ t_{1j}= t_{13}=13

max tij= t61=27max\ t_{ij}=\ t_{61}=27

min t1j<max tijmin\ t_{1j}<max\ t_{ij}


min tmj=t64=14min\ t_{mj}= t_{64}=14

min tmj<max tijmin\ t_{mj}< max\ t_{ij}


So, optimal solution to this problem cannot be obtained.