identify the three conditions that a critical path must satisfy
The three conditions that a critical path must satisfy are:-
All the project activities should be clearly defined and identified.
The technological sequence between the activities must be indicated.
A network must be constructed which shows the relative priority relationships.
The execution periods for each activity should be estimated.