Answer to Question #190807 in Operations Research for Raa

Question #190807

To state whether the following is true or false with a short proof or a counter example in support of the answer :

The following 4/3/F/F_ max problem can be reduced to a machine problem:

Job Processing time (in hours) on

M₁ M₂ M₃

1 8 6 10

2 5 2 13

3 4 11 11

4 6 7 10




1
Expert's answer
2021-05-17T01:21:02-0400

Yes The following max problem can be reduced to a machine problem.


Consider we have 4-job, 3-machine shop as shown in the diagram below-


"x_i=m_1+m_2\\\\y_i=m_3+m_2"








Idle time of machine 1 =46-25=21 min

Idle time of machine 2=46-24=22 min

Idle time of Machine 3=46-38=12min


So, Above problem can be reduced to machine problem.