32Men working at the rate of 9hrs aday can complete apiece ofwork in 7 days.how many more men working at therate of 8hrs a day would complete the work in 6days
1
Expert's answer
2022-03-08T05:53:02-0500
Number of men required to complete the work in 6 days =89×67×32=42