The basement for a house is being excavated and the rectangular hole measured 11m by 14,5m by 4m. The soil is being hauled away in a dump truck which has a an open- box bed of 4m by 3m by 200cm. The truck can't be overloaded at anytim. How many trips will the dump truck have to make to haul away all the soil?


1
Expert's answer
2022-02-21T17:52:22-0500

Number of trips required=Volume of the soil excavatedVolume of the dump truck\text{Number of trips required} =\dfrac{\text{Volume of the soil excavated}}{\text{Volume of the dump truck}}

Given, the measurements of the rectangular base for the house being excavated and the measurements of the dump truck.

Here, 200cm = 2m.

Therefore,


Number of trips required=11×14.5×44×3×2=63824=26.5827\text{Number of trips required} =\dfrac{11\times14.5\times4}{4\times3\times2}= \dfrac{638}{24}=26.58\simeq 27

Hence we require 27 trips to haul away the soil.


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!
LATEST TUTORIALS
APPROVED BY CLIENTS