What and Define scheduling by PERT and CPM in mathematical foundations of computer science

1
Expert's answer
2022-01-11T09:05:45-0500

Solution:

1. Project Evaluation and Review Technique (PERT) :

PERT is appropriate technique which is used for the projects where the time required or needed to complete different activities are not known. PERT is majorly applied for scheduling, organization and integration of different tasks within a project. It provides the blueprint of project and is efficient technique for project evaluation.

2. Critical Path Method (CPM) :

CPM is a technique which is used for the projects where the time needed for completion of project is already known. It is majorly used for determining the approximate time within which a project can be completed. Critical path is the largest path in project management which always provide minimum time taken for completion of project.


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
APPROVED BY CLIENTS