"...30 kilometers (km) of air strip in 6 month it takes 450 workers to do the job"
= > 5 km of air strip in 1 month it takes 450 workers to do the job
Still left 30+10 = 40 (extended road)
40 km for 4 months.
10 km for 1 months
"5 km of air strip in 1 month it takes 450 workers to do the job "
=> for 2*5 km of air strip in 1 month it takes 2*450 workers to do the job.
The agency must have
2*450 workers = 900 workers.
To complete the strip on time the agency should hire
900-450 = 450 workers.