Answer on Question #36438 – Math – Algebra
Question
Jason is considering purchasing a new machine to make plastic silverware. The machine produces 1,000 pieces of silverware in two hours. One box contains 50 pieces of silverware and sells for $3.00. If the machine cos $9,000 and runs for 24 hours a day, how many days will it take to make enough silverware to pay for itself?
Solution
The machine produces 1000/2=500 pieces of silverware per hour, which form 500/50=10 boxes per hour and sells for 10× $3.00=$30.00 per hour.
If the machine runs for 24 hours a day and costs $9,000, then it will take 9000/30=300 hours, which is equal to 12 days 12 hours because 300=24× 12 + 12.
Answer: 12 days 12 hours.
Answer provided by https://www.AssignmentExpert.com
Comments
Thank you for correcting us.
this is the wrong answer. 500 pieces per hour, not 1000 as stated. The correct answer is 12,5days
Dear customer, Please submit your question with all requirements as an assignment to our control panel and we'll assist you.
Wow, thanks, but i do have more