Khuzawayo Construction a local sub-contractor expects to use 19 675 pockets of cement for 2021. Carrying costs are R 6.25 per unit and order costs are R 43.55. The organization works 315 Days per year. Determine the length of the order cycle.
The number of pockets of cement that is equivalent to carrying cost=(19675*6.25)/43.55
=2823.6
=2824 full pockets of cement.
Total pockets=2824+19675
=22,499 pockets of cement
Order Cycle=(315*24*60*60)/22,499
=1,209.65secs/order