3. Consider a job which requires four activities - cutting,assembly,finishing
and packaging.four workers are employed to perform these activities. The
time required by them to perform these activities are as. 5
Activities Worker-1 Worker-2 Worker-3 Worker-4
C 14 12 15 15
F 21 18 18 22
A 14 17 12 14
P 6 5 3 6
How should these activities to be assigned to the workers, so that the job is completed in minimum time
Comments