Question #193330

Compute performance eating of Juan in a given task with the Following information.

*Normal Time= 5 hours

*Standard Personal Time = 30 minutes

*Standard Allowance for Delay=10 minutes

*Actual time of work= 450 minutes


Compute the efficiency and utilization rate of a plant with the given data


1
Expert's answer
2021-05-17T12:18:02-0400

Efficiency = standardornormallaborhoursActualtimeforwork×100\frac{standard or normal labor hours}{Actual time for work} \times 100

= standard normal labor hours ÷\div Actual time for work ×\times 100


standard normal labor hours( 5×60\times 60 )= 300 minutes


Actual time for work = 450 minutes


Efficiency = 300450×100=66.67\frac{300}{450} \times 100= 66.67 %


Utilization Rate = billabetimetotalhoursavailabe×100\frac{ billabe time }{total hours availabe} \times 100


Billable time = Standard time normal time - standard personal time- delays in time


= 300- 30 -10 = 260 minutes


Utilization Rate = 260300×100=86.67\frac{ 260 }{300} \times 100 = 86.67 %




Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!
LATEST TUTORIALS
APPROVED BY CLIENTS