Compute performance eating of Juan in a given task with the Following information.
*Normal Time= 5 hours
*Standard Personal Time = 30 minutes
*Standard Allowance for Delay=10 minutes
*Actual time of work= 450 minutes
Compute the efficiency and utilization rate of a plant with the given data
Efficiency = "\\frac{standard or normal labor hours}{Actual time for work} \\times 100"
= standard normal labor hours "\\div" Actual time for work "\\times" 100
standard normal labor hours( 5"\\times 60" )= 300 minutes
Actual time for work = 450 minutes
Efficiency = "\\frac{300}{450} \\times 100= 66.67" %
Utilization Rate = "\\frac{ billabe time }{total hours availabe} \\times 100"
Billable time = Standard time normal time - standard personal time- delays in time
= 300- 30 -10 = 260 minutes
Utilization Rate = "\\frac{ 260 }{300} \\times 100 = 86.67" %