Compute performance eating of Juan in a given task with the Following information.
*Normal Time= 5 hours
*Standard Personal Time = 30 minutes
*Standard Allowance for Delay=10 minutes
*Actual time of work= 450 minutes
Compute the efficiency and utilization rate of a plant with the given data
Efficiency =
= standard normal labor hours Actual time for work 100
standard normal labor hours( 5 )= 300 minutes
Actual time for work = 450 minutes
Efficiency = %
Utilization Rate =
Billable time = Standard time normal time - standard personal time- delays in time
= 300- 30 -10 = 260 minutes
Utilization Rate = %