Question #186167

Q.1 If Mr. Ahmed is removing the layers in the agency and increasing its span of managerial control, what change would be considered? Please mention its name in the bullet point and further and discuss what happens in such kind of change?


1
Expert's answer
2021-04-28T11:48:47-0400

Reducing the layers in an organization's management is desirable since it minimizes the operational costs that the firm incurs to pay for some leaders in the management chain. Besides, Ahmed will increase his managerial control of workers since he will be close to the junior employees of the firm. Thus, the change that will be considered during removal of some managerial layers is reduction of a firm's expenditure and increases in managerial effectiveness. On the same note,the reduction of layers is known as delayering process.


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS