Power station A delivers 640 MVA to its consumers at a power factor of 0.766 lagging.
Power station B delivers 560 MVA to its consumers at a power factor of 0.7071 lagging.
Two three-phase generating power stations A and B work at (86.077+j18.296) kV and (131.277+j13.798) kV respectively.The two power stations are inter-connected via a transmission line with an impedance of (6.59+j16.672) Ω/phase. The phase-regulator at power station A is adjusted such as to reduce the loading at power station A by 82 MW.
Take machine A as leading machine.
Use standard formulae to the following calculations.
Determine the total active power delivered or received by Power station A (Pi) in MW