A construction company has an opportunity to submit a bid for the construction of a new apartment building. From the specification provided by the developer, the PERT network along with the three time estimate (in week) for each activity as shown in figure-1.
Expected time of each activity:
tE ="\\frac{ to + 9t + tp}{6}" , where;
to = optimistic time
tE = most likely time
tp = pessimistic time
Event Earliest expected time Latest allowable time
1 0 0
2 10 10
3 9 11
4 19 19
5 30 30
6 30 33
7 30 30
8 36 39
9 40 40
10 48 48
Activity Expected time of completion (tE)
A (1-2) 10
B (1-3) 9
C (2-4) 9
D (3-4) 8
E (2-6) 7
F (4-5) 11
G (3-7) 5
H (6-8) 6
I (5-10) 11.67
J (7-9) 10
K (8-10) 9
L (9-10) 8
Comments
Leave a comment