A contractor is trying to estimate the distance to be expected of drawdown of 4.81 m from pumping well under the following conditions:
a) Pumping rate 0.028 m3/s
b) Pumping time = 1066 days
c) Drawdown in observation well = 9.52 m
d) Observation well is located 10.0 m from the pumping well
e) Aquifer material = medium sand
f) Aquifer thickness = 14.05 m
Assume that the well is fully penetrating in an unconfined aquifer.
K = 1.4 "\\times" 10-4m "\\times" s-1
h1 = 14.05 - 9.52 = 4.53 m (h1)2 = 20.52
h2 = 14.05 - 4.81 = 9.24 m (h2)2 = 85.38
"\\frac{r2}{10.0}" = 10.0"\\times" 2.7699
r2 = 27.70m