A concrete mixture needs 660 kg dry sand and 1240 kg dry stone. It is known that the water
content of the existing sand is 4% and that of the stone is 1%. Calculate the amount of wet
sand and wet stone respectively.
% moisture content= ((Weight of wet sand (M)- weight of dry sand (D))/ Weight of dry sand (D)
4%= (M-660kg)/660kg
0.04*660kg= M-660kg
26.4kg=M-660kg
M=660kg+26.4kg
M= 686.4kg
Weight of wet sand= 686.4kg
% moisture content= ((Weight of wet stone (S)- weight of dry stone (D))/ Weight of dry stone (D)
1%=(S-1240kg)/1240kg
0.01*1240kg= S-1240kg
12.4kg=S-1240
S=1252.4kg
weight of wet stone= 1252.4kg