Question #221581

calculate development length required to be provided for m25 concrete and fe415 steel of diameter phi for bar in tension zone and in compression zone

Expert's answer


Development length under Tension:

stress in bar = 415 Mpa

Bond stress M25 = 1.44

Diameter = phi

l.d = (415Φ)/(41.441.6)(415 * \Phi) / (4 * 1.44 * 1.6)

l.d = 45.03Φ45.03\Phi

Development Length under compression

l.d = (415Φ)/(41.441.25)(415 * \Phi) / (4 * 1.44 * 1.25)

l.d = 57.639Φ\Phi