The following data are extracted from the current year’s budget of J.J. Trading.
Direct labour hours Hourly wage rate Production overhead
Machine shop 20,000 RM3.25 RM70,000
Assembly shop 18,000 RM3.10 RM45,000
Finishing shop 10,000 RM3.00 RM20,000
A customer has requested a quotation for supplying a special piece of equipment and the estimator has worked out the following details:
Components to be purchased RM216
Materials from store RM270
Direct labour times:
Machining 80 hours
Assembling 40 hours
Finishing 30 hours
Delivery cost to customer RM60
Administration and marketing costs are covered by adding 10% to cost of manufacture. 12 ½% is added to the total (delivered) cost for profit.
You are required to :
(a) Calculate the cost for supplying this special piece of equipment.
(b) Calculate the selling price quoted to the customer.