The estimated production of an organisation is 500000 units. The standard man hours required to produce each unit is 5 hours. The past experience show that the workability of each employee in a man hours is 2000 hours per year . How many workers are required to produce estimated units

1
Expert's answer
2021-12-27T13:42:37-0500

Total Production=500,000 Units

Man hours per unit= 5hours

Total number of hours required to produce the 500,000 units

"=500000*5= 2,500,000 Hours"

Hours per employee per year= 2000 Hours

"No. of employees required to produce 500,000 units= Total number of hours required to produce the 500,000 units\/Hours per employee per year\n= 2,500,000\/2000\n=1250 Workers"