Question #282451

The estimated production of an organisation is 500000 units. The standard man hours required to produce each unit is 5 hours. The past experience show that the workability of each employee in a man hours is 2000 hours per year . How many workers are required to produce estimated units

1
Expert's answer
2021-12-27T13:42:37-0500

Total Production=500,000 Units

Man hours per unit= 5hours

Total number of hours required to produce the 500,000 units

=5000005=2,500,000Hours=500000*5= 2,500,000 Hours

Hours per employee per year= 2000 Hours

No.ofemployeesrequiredtoproduce500,000units=Totalnumberofhoursrequiredtoproducethe500,000units/Hoursperemployeeperyear=2,500,000/2000=1250WorkersNo. of employees required to produce 500,000 units= Total number of hours required to produce the 500,000 units/Hours per employee per year = 2,500,000/2000 =1250 Workers



Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!
LATEST TUTORIALS
APPROVED BY CLIENTS