Question #20343

A project has an initial requirement of $261,000 for fixed assets and $27,000 for net working capital. The fixed assets will be depreciated to a zero book value over the 4-year life of the project and have an estimated salvage value of $78,000. All of the net working capital will be recouped at the end of the project. The annual operating cash flow is $96,200 and the discount rate is 13 percent. What is the project's net present value if the tax rate is 35 percent
$42,011

$43,333

$45,799

$47,880

$47,919

Expert's answer

A project has an initial requirement of $261,000 for fixed assets and $27,000 for net working capital. The fixed assets will be depreciated to a zero book value over the 4-year life of the project and have an estimated salvage value of $78,000. All of the net working capital will be recouped at the end of the project. The annual operating cash flow is $96,200 and the discount rate is 13 percent. What is the project's net present value if the tax rate is 35 percent

$42,011

$43,333

$45,799

$47,880

$47,919

Answer


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

LATEST TUTORIALS
APPROVED BY CLIENTS