Question #299340

Question 2



The budgeted and standard data for productivity include the following



Direct labour



Ten employees work for 45 hour a week. The standard rate of pay is ksh 4 per hour. Output per hour is 40 kg of the product.



Direct material



Material quantity kg price per kg



X 60 2.00



Y 40 1.00



Z 100 1.40



From this standard matrix 180 kg of product is expected



Actual data for first week in April were as follows



Hours worked 45



Rate of pay ksh 4 per hour



Overhead incurred ksh 5400



Output 1980 kg



Production and consumption of materials were as follows:



Material Quantity (kg)



X 700



Y 440



Z 1120




Required



(a) Calculate the following direct material variance for each material (10mks)



i. Total



ii. Price



iii. Usage



iv. mix



(b) Calculate the direct labor efficiency variance (10mks)

Expert's answer

The answer to your question is provided below

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

LATEST TUTORIALS
APPROVED BY CLIENTS